Cost Worksheet Log Window

Overview:

The Cost Worksheet log window provides a central location for analyzing budgeted, committed, and actual project costs. From this window, you can review cost items or add new cost codes. You must create cost codes before you can distribute costs to the Cost Worksheet. This topic describes the following:

Buttons, Drop-Down Lists, Icons, and Links:

Add Cost Code add_button.jpg button

Click this button to open the Cost Worksheet dialog box to add a new cost code to the cost worksheet.

Print Report print.bmp button

Click this button to print the default cost worksheet report.

Print Preview print_preview.bmp button

Click this button to display the default log report on screen the way it will look when it is printed.

Select an Action drop-down list

Click the arrow next to the Select an Action drop-down list  to open the drop-down list containing actions you can perform. These include printing the selected document, exporting or importing a document, sending the document to Excel, adding a cost code, Recalculating the worksheet, or  using Advanced print to print the report, form, dunning letter or creating or viewing versions of the cost worksheet log.

Notes:

Send layout to Excel send_layout_to_excel.bmp icon

Click the send_layout_to_excel.bmp icon to send the current log layout to an Excel spreadsheet. This functionality is not available when using the Firefox Internet browser.

Transmittals Queue link

Click this link to display the items in the Transmittals list. From there you can select the create or remove functions you want to perform on a transmittal.

Layout drop-down list  

Use this drop-down list to select a different layout for the log window. For more information on layouts, see Layouts Overview.

Edit icon docpencilicon.bmp

Click the docpencilicon.bmp icon in the left column to open the Cost Worksheet document window in Edit mode.

Find link

Click the Find link to find a particular word or text in all documents in the Cost Worksheet log window.

Control Center link

Click to return to the Workspace.

Transmittals Queue link

Click this link to display the items in the Transmittals list. From there you can select the create or remove functions you want to perform on a transmittal.

Back to the top

Columns:

Cost Code

The "name" of the cost code. Cost codes categorize the different types of work associated with a project. Each cost code can contain up to 30 alphanumeric characters. Click to open the Cost Worksheet document window in View mode.

Note:

If you have administrator rights, you can edit the cost codes.

Title

A description of the cost code.

Original Budget

Costs that have been distributed from a contract, PO, or trend.

Approved Budget Revisions

Costs that have been distributed from an approved Change Order or trend.

Revised Budget

The sum of the Original Budget and the Approved Budget Revisions.

Pending Budget Revisions

Costs distributed from a Proposal, a pending Change Order, or trend.

Estimated Budget Revisions

Cost estimates distributed from a trend.

Budget Adjustments

Costs distributed from a trend.

Projected Budget

The sum of the Original Budget, the Approved Budget Revisions, the Pending & Estimated Budget Revisions, and the Budget Adjustments.

Original Commitment

Costs distributed from a contract, PO or trend.

Approved Commitment

Costs distributed from an approved change order or trend.

Revised Commitment

The sum of the Original Commitment and the Approved Commitment.

Pending Commitment

Costs distributed from a Proposal, a pending Change Order, or trend.

Estimated Commitment Revisions

Cost estimates distributed from a trend.

Commitment Adjustments

Costs distributed from a trend.

Projected Commitment

The sum of the Original Commitment, the Approved Commitment, the Pending & Estimated Commitments, and the Commitment Adjustments.

Actuals Received

Costs distributed from a trend or invoice (if the contract/PO is distributed to Committed).

Actuals Issued

Costs distributed from a trend or invoice (if the contract/PO is distributed to Budgeted).

Original Variance

The Original Budget minus the Original Commitment.

Approved Variance

The Revised Budget minus the Revised Commitment.

Pending Variance

The (Revised Budget + Pending Budget Revisions) - (Revised Commitment + Pending Commitment)

Projected Variance

The Projected Budget minus the Projected Commitment.

Budget Percent

This amount represents the percentage of the total amount budgeted for the line item.

Commitment Percent

This amount represents the percentage of the total amount committed for the line item.

Procurement Estimate

The total of the Estimate column on the Bid Tabulation tab of the Procurement Item document window.

Original Estimate

The original estimate of the procurement item up for bid.

Estimate Accuracy

Calculation: Original Estimate - Procurement Estimate.

Estimated Gross Profit

Calculation: Original Budget - Original Estimate. The value will be 0 unless the item is awarded.

Buyout

Calculation: Original Estimate - Original Commitment. The value will be 0 unless the item is awarded.

Purchasing Buyout

Calculation: Procurement Estimate - Original Commitment. The value will be 0 unless the item is awarded.

Planned to Commit

This is the total planned expenditure for each cost code.

Order Code

Use this field to vary the sort order of your worksheet from the cost code order.

Select an Action

This drop-down list appears at the right of each cost worksheet document listed in the log. Click the arrow to open a drop-down list containing actions you can perform, including  printing a report, or recalculating.

Create versions of a Cost Worksheet log

To create a new version of the Cost Worksheet log, choose Version Worksheet from the Select an action drop-down list. Click Yes when prompted to confirm to version the log.

View all versions of the Cost  Worksheet log

To view different versions of the Cost Worksheet log, choose View  Worksheet Versions from the Select an action drop-down list. On the Cost Worksheet Versions dialog box, you can view and access previous versions of the selected Cost Worksheet, identify who created the versions and when the versions were created. You can create and preserve a new version of the Cost Worksheet log at any stage during a project. Use the Version option to maintain a history of your log changes.

Back to the top

How to access this log window:

From the Contract Management Control Center, expand the appropriate project, choose Contract Information, and then choose Cost Worksheet.

For additional help:

For additional help, click the Show link at the top left corner of this help topic. Use the Contents, Index, or the search utility to find additional help.